Question: I signed a contract a little over two years ago to
purchase a to be built condominium unit. I gave the developer a hefty
down payment. My sales contract says that settlement must take place
within two years. On a weekly basis, I inspect the building and it does
not look like a lot of work has been done.
I asked the developer when I will be able to go to closing, and his
response was that because of matters out of his control, he will not be
able to meet the settlement deadline spelled out in the sales contract.
Based on the length of time this has taken, and the declining
condominium market, I would like to cancel the contract and get my
deposit back.
The developer is relying on a paragraph in the contract that excuses
a builder from timely delivery based on "force majeure."
Exactly what does this mean?
Answer: It is French for "major" or
"superior" force.
The Merriam-Webster Online Dictionary defines "force majeure"
as "an event or effect that cannot be reasonably anticipated or
controlled. Some people equate this concept with "an act of
God."
Legal contracts of any kind -- including real estate -- often
include a "force majeure" clause. A sample would read like
this:
Contractor’s failure to perform any term or condition of this
Agreement as a result of force majeure conditions beyond its control
such as, but not limited to, war, strikes, fires, flood, Acts of God,
governmental restrictions, power failures, or damage or destruction,
shall not be deemed a breach of this Agreement.
As we all know, the condominium market has slowed down dramatically
in many parts of this Country. Furthermore, many developers are now
unable (or unwilling) – for a number of reasons – to meet the
targeted settlement dates spelled out in their sales contract.
As a result, I am hearing from attorneys and consumers all over the
country that developers are trying to use the "force majeure"
clause as their legal grounds for not refunding the earnest money
deposits to now unhappy contract purchasers.
The law of contracts is quite clear. A Court will only excuse a
developer from performance when there is an actual impossibility, and
not merely unexpected difficulties. Recently, the District of Columbia
Court of Appeals addressed a case where one party to a contract
attempted to void that document based on a force majeure type clause.
The clause allowed termination of the contract for "any other
emergency beyond the parties’ control, making it inadvisable, illegal
or which materially affects a party’s ability to perform its
obligations under this Contract."
According to the Court:
Such provisions are often called force majeure clauses, but
attaching that label does not assist in our analysis. We must look to
the language that the parties specifically bargained for in the
contract to determine the parties intent concerning whether the event
complained of excuses performance.
What does this mean?
A developer cannot merely say, "I cannot deliver because of
force majeure." That is a label, which is too general. The
developer must justify his position, providing proof that something
truly beyond his control caused the delay in completing your
condominium unit.
Take this example: recently, there was a serious wind and rain storm
in the Washington area. Clearly, this was an "act of God."
But in order to be excused from performance, it is not enough for the
developer to cite to this storm. He must specifically show how and why
the storm specifically impacted on his development.
One lawyer from Florida recently told me that developers in his area
are abusing the concept. Any expense due to increased building costs
are all labeled "force majeure," which seems to be the
"excuse de jeure."
What can you do if you signed a contract for a piece of property and
the time for delivery has elapsed? Send a demand letter to the
developer, in which you include a signed form release. This document
states that the contract is declared null and void and the earnest
money refunded in full back to you. You should sign the release and ask
the developer to do the same.
Your letter should also state that if he is relying on "force
majeure," he should specifically document his claim. The burden is
on the developer to prove not only that there was an unanticipated
event, but how this event directly impacted on the development process.
And unless the developer can justify his position, you are entitled
to a refund. Hopefully, you will not have to go to Court to collect.
A Florida Judge said it all when he wrote:
Inconvenience or the cost of compliance, though they might make
compliance a hardship, cannot excuse a party from the performance of
an absolute and unqualified undertaking to do a thing that is
possible and lawful. Parties ... bind themselves by their lawful
contracts, and courts cannot alter them because they work a hardship.